Synchronisation
There is nothing to do in daily use other than maintaining dimension values, projects and project tasks in Business Central. Every change to a record that is covered by an active dimension mapping is added to the sync queue, and sent to Visma Payroll from there.
Which Changes Are Sent
| Change in Business Central | Result in Visma Payroll |
|---|---|
| Create a dimension value, project or project task | The cost unit is created |
| Change a dimension value, project or project task, for example the name or description | The cost unit is updated |
| Block a dimension value | The cost unit gets yesterday's date as end date (Valid To), so it can no longer be used |
| Block a project, or set its status to Completed | The cost unit gets yesterday's date as end date (Valid To), so it can no longer be used |
| Set an end date on a project task | The cost unit gets the end date of the project task as end date (Valid To) |
| Rename a dimension value, project or project task | The cost unit with the old code is deleted, and a new one is created with the new code |
| Delete a dimension value, project or project task | The cost unit is deleted |
tip
Block a dimension value or a project, or complete the project, instead of deleting it when it is no longer in use. The cost unit then gets an end date in Visma Payroll instead of being deleted.
Sending the Queue to Visma Payroll
The queue is sent to Visma Payroll in two ways:
- Automatically by a job queue entry, at the interval you choose. See Automation
- Manually with the Synchronise Now action on the Visma CostUnit Sync Queue page. See Sync Queue
The queue is only sent when Enabled is turned on in Visma Dimension Setup.