The Visma Calendar Setup page holds the connection to Visma Calendar and decides how hours are transferred to the project journal. Open it by searching for Visma Calendar Setup in Business Central.

General​

FieldDescription
EnabledEnables the service that connects to Visma Calendar

Connection Settings​

FieldDescription
Api keyThe API key provided by Leap IT
Visma IdThe Tenant ID of your company in Visma. See Find your Tenant ID

Project​

FieldDescription
Import DimensionsSpecifies whether the cost units on the registrations are imported. This is turned on by default, and must stay on, since the project and the project task are read from the cost units
Project Journal Template NameThe project journal template that the hours are transferred to
Project Journal Batch NameThe project journal batch that the hours are transferred to
Project Dimension IdThe ID of the cost unit in Visma Calendar that holds the project. The value of this cost unit is used as the project no. in Business Central
Project Task Dimension IdThe ID of the cost unit in Visma Calendar that holds the project task. The value of this cost unit is used as the project task no. in Business Central
Chargeable Dimension IdThe ID of the cost unit in Visma Calendar that decides whether the hours are chargeable. See Chargeable Hours
Set chargeable dimensionsOpens the list of cost unit values that are chargeable. Only available when Chargeable Dimension Id is filled in

Project Journal Template Name, Project Journal Batch Name, Project Dimension Id and Project Task Dimension Id must be filled in before hours can be transferred to the project journal.

Actions​

ActionDescription
Test ConnectionChecks if the connection settings are valid and the system can access Visma Calendar. A message shows whether the connection was established
Work Type MappingOpens the work type mapping

Project Task on the Project​

If a registration in Visma Calendar has no project task, the project task is taken from the field Time Job Task on the project card in Business Central, under General. The field is also available on the project list.

Set Time Job Task on the projects where hours can be registered without a project task. The project task must be of the type Posting. Registrations without a project task are not transferred for projects where the field is empty.

Getting Started​

  1. Enter Api key and Visma Id
  2. Click Test Connection and check that the connection is established. If it fails, check the two fields and try again, or contact Leap IT
  3. Fill in the fields under Project
  4. Set up the work type mapping and the dimension mapping
  5. Turn on Enabled